Canal Building Schedule

7:00 a.m. – 8:00 a.m.

Approx. 7 carpenter volunteers from Local 107 assemble final portions of the canal frame in parking lot at Harding & Winter, assisted by 10 crew volunteers

8:00 a.m.

Harding Street is closed from Temple to Winter

8:00 a.m. – 9:00 a.m.

Carpenters and CanalFest volunteers assemble 75’ long frame in Harding Street, install components and waterproof liner

9:00 a.m. – 10:45 a.m.

Worcester Dept. of Public Works fills Canal with 4,500 gallons of water while landscaper(s) beautify the perimeter

11 a.m. – 6:00 p.m.

Canal Replica open to visitors, guided by National Parks Service rangers from the Blackstone River Valley National Heritage Corridor

6:00 p.m. – 7:00 p.m.

Worcester Fire Dept. pumper truck pumps water out of Canal Replica and into the existing Blackstone Canal beneath Harding St.

7:00 p.m. – 8:00 p.m.

Tear down canal structure and store canal sections